Progress Report of the New Site

As we all know, currently, the construction work is being given to two competent contractors by dividing the whole building in to two, GAFAT Building contractor is building the first phase work of the Elementary school and Kindergarten whereas, Tewodros Building Contractor is doing the first phase of the Girls and Boys dormitory and the administration building.

Therefore, the undergoing constructions are:

1.    Boys Dormitory
2.    Girls Dormitory
3.    Kindergarten
4.    Elementary School
5.    Administration Building

Girls Dormitory

•    One Block of G+1 / Two Story building
•    986 Sq. total built up aria.
•    The sub structure work is 100% completed

- Excavation work 100%

- Concrete work 100%

- Masonary work 100%

             - Expansion Joint work 100%

•    Part of the super structural work is completed as follow:


  - Concrete work 25%

 - Form Work 25%

- Steel Reinforcement 25%


•    The contractor is expected to complete the 1st phase work and hand it over to the client Bridge of Hope with in 30 working days.
 

 Boys Dormitory


•    One Block of G+1 / Two Story building
•    986 Sq. total built up aria.
•    The sub structure work is 100% completed
o    Excavation work 100%
o    Concrete work 100%
o    Masonary work 100%
o    Expansion Joint work 100%
•    50% of Super-structure work is completed
o    Concrete work 50%
o    Form Work 50%
o    Steel Reinforcement 50%
•    The contractor is expected to complete the 1st phase work and hand it over to the client Bridge of Hope within 20 working days.

 Bridge Magdalena Elementary School


•    It is a G+2 Building on an area of 920 Sq.mr ground floor area
•    The sub structure work is 100% completed
o    Excavation work 100%
o    Concrete work 100%
o    Masonary work 100%
o    Expansion Joint work 100%
•    40% of Super- Structure work is completed
o    Concrete work 40%
o    Form Work 40%
o    Steel Reinforcement 40%
•    The contractor is expected to complete the 1st phase work and hand it over to the client Bridge of Hope within 20 working days.
 

 Kindergarten


•    It is a G+0 Building
•    Builtup ground floor area is 750 Sq.mr.
•    Sub-structure work is 100% completed
o    Excavation work 100%
o    Concrete work 100%
o    Masonary work 100%
o    Expansion Joint work 100%
•    Super-Structure work is also 100% completed
o    Concrete work 100%
o    Form Work 100%
o    Steel Reinforcement 100%
•    The contractor is ready to hand it over to the client Bridge of Hope in order to let us to proceed to the 2nd phase.
 

 Administration Building


•    One block of G+2 Building
•    450 Sq.mr of builtup area
•    98% of the sub-structural work is completed
o    Excavation work 100%
o    Concrete work 98%
o    Masonary work 98%
o    Expansion Joint work 98%
•    20% of Super-Structure work is completed
o    Concrete work 20%
o    Form Work 20%
o    Steel Reinforcement 20%
•    The contractor is expected to hand it over to the client within 60 working days.
 